APPENDIX B Sample Migration Task Lists
119
Perform User Acceptance Tests
1 Perform acceptance tests.
2 Compare acceptance test results to baseline.
3 Analyze acceptance test results.
4 Perform corrective actions.
5 Retest as necessary.
6 Document acceptance test results.
7 Obtain user signoff on acceptance test results.
Perform Production Data Refresh
1 Schedule production data cutover.
2 Extract production data.
3 Move data to target.
4 Load data into Adaptive Server production environment.
5 Backup new environment.
6 Notify users of data refresh.
Parallel Migration Task List Example
This sample task list covers a parallel migration with replication approach
to upgrade an older system to Adaptive Server Enterprise 12.5.
The scenario for this task list is:
• A major telecommunications company cannot afford system
downtime for the upgrade.
• In the event of failure, the system cannot be down more than 15
minutes and the company cannot afford more than 1 hour of data loss.
The migration must support these contingency requirements if a
production back-out is required.
This example does not repeat the preparation steps to given in the previous
example. The task lists for this example include: